Abadan Gas Power Plant
Project Introduction

- Project Properties :

1.Construction of 1200 Precast Concrete Piles.The length of the Piles were 24 m & with 40*40(cm) Section.

2. Driving of 1200 Precast Concrete Piles.The length of the Piles were 24m & with 40*40(cm) Section.

3. Chipping The Piles And Earth Work.